Decentralized electricity storage
at AB InBev
With the installation of battery storage solutions, the world's leading brewing company Anheuser-Busch InBev is taking an important step towards sustainability. In cooperation with EDF power solutions, battery storage systems will be installed at four locations in Germany. In 2023, the first battery storage system was put into operation at Beck's in Bremen. In addition, three more battery storage systems will be installed at Spaten-Löwenbräu in Munich, at Hasseröder in Wernigerode, and at Diebels in Issum.
Anheuser-Busch InBev has signed a ten-year contract with EDF power solutions Deutschland: EDF power solutions offers a full-service package from planning to installation and operation, and also covers the investment costs.

Beck's Bremen
In November 2023 the battery storage system in Bremen was commissioned. The battery is designed to supply the production plant with 1.6 MW for at last an hour.

- 1.6 MW power
- 1.9 MWh capacity
- 192 modules, 8 racks
- Lithium Nickel Manganese Cobalt Oxydes (NMC)
- 20-foot container
- Connection to the medium-voltage grid
- Potential cost savings per year: 238,000 Euro
Hasseröder Wernigerode
In June 2024, the second battery storage system for AB InBev was put into operation. Here, the battery can supply the brewery with at least 1.4 MW for one hour.

- 1.3 MW power
- 1.4 MWh capacity
- 144 modules, 6 racks
- Lithium Nickel Manganese Cobalt Oxydes (NMC)
- 20-foot container
- Connection to the medium-voltage grid
- Potential cost savings per year: 155,480 Euro
Löwenbräu-Spaten München
The third and largest battery storage system in Munich was put into operation in autumn 2024. This system will supply the company with at least 1.7 MW for one hour.

- 1.7 MW power
- 2 MWh capacity
- 192 modules, 8 racks
- Lithium Nickel Manganese Cobalt Oxydes (NMC)
- 20-foot container
- Connection to the medium-voltage grid
Construction of the storage system in Munich
Diebels Issum
A storage system with a capacity of 300 kW is being built at the Diebels brewery in Issum. Completion and commissioning for the project are planned for 2025.
Services by EDF power solutions Deutschland
- Analysis of load and location including battery sizing
- Financing: Coverage of all investments
- Coverage of necessary application procedures (building permit and grid connection)
- Installation: Battery procurement, connection and commissioning
- Regular preventive maintenance and battery control
Any questions? Let’s talk!